Asbestos Removal Case Studies for Work Completed in North Wales, Mid Wales, Cheshire, and Shropshire

No job is too small or too big for our team here at A&D Environmental Services Ltd. We have all the skills and experience necessary to assess, manage and deliver the right solutions that comply with regulations and legislation. Plus, we always ensure we complete a project on time and to your budget.

See below for our asbestos removal case studies we have managed.

Removal of asbestos insulation boarding forming the first-floor ceiling to a lift shaft

Scope: The removal of asbestos insulation boarding forming the first-floor ceiling to a lift shaft
Client: Health Board Estates Department
Sector: Health

The lift car was raised and made safe (isolated by the appointed lift engineers)

A fixed scaffold was installed beneath the lift car and a crash deck built above the lift car to provide safe access to the ceiling boards.

Due to the location of the works and complicated transit procedure through occupied areas of the hospital, a modular self-contained decontamination unit was used and located within the adjacent Waiting Room – the floor was protected with 2mm Correx sheeting.

An enclosure was built on the 1st floor over the lift doors protected from Staff and Visitors with plywood sheeting. Within the ceiling void to complete the enclosure, a timber framed polythene pod was built over the asbestos ceiling boards. A negative pressure unit was sighted within the ceiling void and the exhaust tubing directed through the main roof and expelled to atmosphere.

The appointed analytical consultant conducted pre-start background air monitoring within the adjacent corridor prior to any asbestos removal works commencing.

As part of their remit, the analytical consultant continued reassurance testing in the corridor and offices as the works progress with all results printed off and made available to the building users and staff.

Project completed on time and with minimum disruption to the hospital ward.

Safe removal and disposal of the asbestos content vinyl floor tiles

Scope: The safe removal and disposal of the asbestos content vinyl floor tiles and environmental clean of the floor areas totalling 104m2.
Client: Health Board Estates Department
Sector: Health

Works carried out from 6pm onwards Friday evening within the fracture clinic foyer and from 8.30 pm onwards within the ground floor corridor to minimise disruption to hospital operation.

Overlay flooring on removal with 3mm thick hardboard sheets secured with 68mm wide black PCL cloth tape. Black and yellow hazard warning tape to be used on the edges of boards where they meet the existing modern flooring until new flooring can be laid by the appointed flooring contractor.

A&D ENVIRONMENTAL SERVICES LTD

VICTORIA PIER – COLWYN BAY

A&D Environmental Services is pleased to have been granted the contract to remove asbestos-containing materials identified within the structure and buildings on Victoria Pier, Colwyn Bay.

The Pier was opened in 1900 and thrived over the years and during its heyday extended to 227m in length, but following a decline was forced to close in 2008 and in the interim its structure became unsafe, and parts of the pier began to collapse.

Working in conjunction with Conwy County Council, the nominated Demolition Contractor and with the involvement of HSE Inspectors and other stakeholders, a safe system of work was established to mitigate the various hazards presented by a building of this type and current condition.

We commenced work in February 2018 with our team of licensed asbestos removal contractors working in a phased approach, and we were able to complete the project on time in early June 2018.

A&D ENVIRONMENTAL SERVICES LTD

MAINTENANCE WORKS TO STEAM RECOVERY VESSEL

Scope: Maintenance Works to Steam Recovery Vessel
Client: Major Food Manufacturing Site
Sector: Thermal insulation + sheet metal cladding
Project Duration: 4 weeks
The client requested existing uninsulated services vessels (3 off) to be insulated with BCO CFC Free Rockwool insulation, 75mm thick and then to be over-clad with stainless steel sheet metal finish. All laps and joints arranged to shed water, to prevent water ingress to insulation material, finally sealed with clear silicone mastic.

New service pipework, valves, and flange joints were insulated to the same specification and similarly over clad with stainless steel finish 304S which is specified for use with food processing industries, chemical manufacturing plants, etc.

The work was completed on time with minimal disruption to the continuous shift working pattern which the Client operates at this site. The team of A&D Environmental thermal insulation engineers are well trained and experienced in working in this type of manufacturing facility where high standards of food safety in addition to health, safety and environmental controls are expected and maintained by employees and contractors alike.

A&D ENVIRONMENTAL SERVICES LTD

CONTAMINATED LAND REMEDIATION

Scope: Contaminated Land Remediation
Client: Local Authority.
Sector: Former Refuse Site identified as containing asbestos containing materials within the topsoil capping which required grading and contouring by Civil Engineering contractors to maintain the site’s integrity.
Project Duration: 3 weeks

The Local Authority client was granted permission by Natural Resources Wales to move contaminated soil from one side of the landfill site to the other side of the landfill to prevent surcharging on the site.

A&D Environmental Services notified the HSE with a scope of works to assist the nominated Civil Engineering contractors with the soil transfer by fine misting the topsoil to suppress fibre release.

Also to provide a watching brief to identify, isolate and dispose of Asbestos Containing Materials (ACM) disturbed during the earth moving process. In addition to providing appropriate asbestos awareness training, provision of RPE/PPE and decontamination procedures for the machine operators.

On completion of the project, the Local Government Officer in charge of the contract provided the following testimonial:-

“I would also like to thank yourselves for your support and excellent service to complete the project, especially in the time frames we were working to.
Look forward to working with you again.”

A&D ENVIRONMENTAL SERVICES LTD

HAFOD Y GEST PORTHMADOG

Scope: Asbestos Removal as part of demolition and rebuild
Client: Major Building Contractor
Sector: Former Council Care Home built in the 1970s which no longer could meet the needs of older people, to be replaced with high-quality modern accommodation and care facilities for older people in the area.
Project Duration: 3 months

The vacated building contained asbestos insulation board (AIB) ceiling tiles throughout the building which also had stud wall separation within rooms. The planned works involved the controlled removal of the AIB ceiling tiles and associated MMMF insulation and debris within the ceiling voids above, also to remove one face to stud wall to reveal any entrained asbestos debris for removal and subsequent demolition of the building by the Principal Contractor.

The works were phased to account for the layout of the building dividing its floor plan into manageable areas to allow for safe transit for operators and waste removal, also to maintain emergency exits as a precaution.

Works were completed on time without disruption to the Principal Contractor’s schedules and providing on-going support as necessary as the project developed into the demolition and building phases.

The Site Manager representing the Client provided the following
testimonial:-

“I would like to thank you all for the hard work your lads put in at Hafod y Gest, they were all a pleasure to have on site and very professional, a job well done.”

A&D ENVIRONMENTAL SERVICES LTD

01352 734 498

Contact us today for more information on our asbestos removal case studies.

A&D ENVIRONMENTAL SERVICES LTD

ACCREDITATIONS

A&D ENVIRONMENTAL SERVICES LTD

ACADOTICAOConstruction OnlineSafe ContractorSSIPUVDBWPA